LS Cable & System said it won a competitive tender from Korea Electric Power Corporation to expand the subsea grid between Hwawon in Haenam and Anjwa Island in Sinan, South Jeolla Province. The project will add about 14 km of 154 kV subsea cable to increase the existing link’s transmission capacity. LS Cable & System will supply the cable, and LS Marine Solution is expected to lay it. The company is targeting completion in December 2028.
Questions for local governments in Korea
- When will the additional grid connection capacity be allocated to projects, and by what criteria?
- Who will coordinate and communicate construction schedules in areas where work overlaps with fishing activity?